A 3 metre single-storey extension fixes the kitchen on most London terraces. It doesn’t do anything for a dark middle room, and it doesn’t add a bedroom. When that’s the problem, there are two bigger options: go round the side as well as out the back, or build up over the extension.
Both cost more than a standard rear extension, and both bring structural and planning issues that the smaller job doesn’t have.
Wraparound: side and rear in one L
A wraparound fills the side return beside the outrigger and carries on across the back of the house, so the new floor wraps the old back corner in an L shape. On a Victorian terrace it’s usually the most ground-floor space you can add without losing most of the garden. It also gets rid of the awkward corner where the outrigger meets the main back wall, which neither half fixes on its own.
What’s in the side passage changes the job. Usually it’s the drains: the soil stack from the back addition, an inspection chamber, and often a shared run serving several houses. Since October 2011 most of those shared runs have been public sewers, so building over one needs Thames Water’s agreement first. That should come out of a CCTV drain survey before the design is fixed, not out of the trench in week three.
Double storey: the same footprint twice
A double storey extension is usually a rear extension with a bedroom or bathroom on top. Scaffolding, roof, foundations and disruption are paid for once and you get roughly twice the floor. Per square metre it’s normally the cheapest way to add space to a London house. If a bedroom is going to be needed in a few years anyway, building it now costs far less than coming back for it.
The two floors aren’t the same job done twice, though. Everything below has to carry what’s above. That usually means deeper footings, heavier steel and sometimes work to the existing house that wasn’t expected.
Which house suits which
The house usually decides.
A terrace with a side return and a reasonable garden is the usual wraparound. Going up at the back is often limited by how close the rear boundary is and by the neighbours’ windows.
A semi with a deep garden is the usual double storey. There’s room to go out without losing the garden, and the roof is simpler to tie into.
A detached house can generally take either.
If what you need is one more bedroom and nothing else, price a loft conversion first. On a lot of London houses it costs less and leaves the garden alone. For the single-storey choice on its own, see side return vs rear extension.
Planning: where permitted development stops
The two diverge here.
Wraparound. A side return and a rear extension might each pass permitted development separately. Joined into one L, they usually don’t. The usual reading, set out in the government’s technical guidance, is that an extension going beyond both the rear wall and a side wall has to meet both sets of limits at once. The side extension limit is half the width of the original house, and an L running across the whole back is wider than that. Most London wraparounds go in as a full application.
There’s a second trap if the house already has an older extension, say a 1980s kitchen off the back. Class A adds it in:
“any total enlargement (being the enlarged part together with any existing enlargement of the original dwellinghouse to which it will be joined) exceeds or would exceed the limits set out in sub-paragraphs (e) to (j)”
GPDO 2015, Schedule 2, Part 1, Class A.1(ja)
“Original” means the house as built, or as it stood on 1 July 1948 for anything older. That’s the date the Town and Country Planning Act 1947 came into force. Anything a previous owner added after that counts.
Double storey. A two-storey rear extension can be permitted development, but the limits are much tighter:
“the enlarged part of the dwellinghouse would have more than a single storey and— (i) extend beyond the rear wall of the original dwellinghouse by more than 3 metres, or (ii) be within 7 metres of any boundary of the curtilage of the dwellinghouse being enlarged which is opposite the rear wall of that dwellinghouse”
GPDO 2015, Schedule 2, Part 1, Class A.1(h)
On a terrace with a 10 metre garden, a 3 metre deep two-storey extension leaves exactly 7 metres. Anything less and it’s a full application. In a conservation area, a rear extension of more than one storey isn’t permitted development at all.
Even when it is permitted, Class A comes with conditions. The one that changes the design of a first-floor room is about side windows:
“any upper-floor window located in a wall or roof slope forming a side elevation of the dwellinghouse must be— (i) obscure-glazed, and (ii) non-opening unless the parts of the window which can be opened are more than 1.7 metres above the floor of the room in which the window is installed”
GPDO 2015, Schedule 2, Part 1, Class A.3(b)
So the new bedroom gets its light from the rear wall or a rooflight, not from a clear window looking at next door. The same paragraph requires materials “of a similar appearance” to the existing house, and the roof pitch of a two-storey addition has to match the original as far as practicable.
Councils also apply the 45-degree test to neighbours’ windows when they assess an application. At first-floor level that’s where most objections come from.
The planning and design stage should find these limits before drawings get detailed. A design built around what the council will approve costs less than a better one that’s refused. Building regulations apply in every case, separately from planning.
Party walls on a bigger job
Both types usually involve the party wall. Steels bearing on it, cutting in for flashings, raising it for a two-storey flank, or underpinning it are all section 2 rights, and the notice for those is in section 3:
“A party structure notice shall— (a) be served at least two months before the date on which the proposed work will begin; (b) cease to have effect if the work to which it relates— (i) has not begun within the period of twelve months beginning with the day on which the notice is served; and (ii) is not prosecuted with due diligence.”
Party Wall etc. Act 1996, section 3(2)
The twelve-month expiry catches people whose planning takes longer than expected. Serve too early and the notice can lapse before the builder starts. If the neighbours dissent, surveyors are appointed and an award is agreed, which adds weeks.
Structure you don’t see afterwards
Foundations. Victorian footings are often a few courses of stepped brick on clay, much shallower than anything built today. London clay shrinks and swells with the seasons, and near trees the new footings may go well over a metre deep. Put a second storey on and either the new foundations are kept independent with a movement joint to the old, or part of the existing house is underpinned. On the Chiswick rear extension, even a single storey needed footings deeper than the original.
Steel. A wraparound opens up two walls of the existing house and usually needs a goalpost frame, two columns and a beam, plus a corner post or a cantilever where the old outrigger corner was. Padstones are sized by the engineer. Steel has a lead time, often two to four weeks from approved drawings, and the programme waits if it’s ordered late.
Drainage. Build-over agreements with Thames Water take weeks, and inspection chambers often have to move.
The roof junction. On a double storey, the new roof has to tie into the old one with flashings and a proper path for the water. Badly detailed, that’s where leaks start.
The survey and structural design need doing before anyone fixes a price. That’s what the pre-construction stage is for.
Cost and time
Broad London ranges, build cost only, before kitchens, bathrooms and VAT:
| Type | Typical size | Build cost | On site |
|---|---|---|---|
| Wraparound | 25 – 35 m² | £110,000 – £165,000 | 14 – 20 weeks |
| Double storey rear | 25 – 40 m² total | £90,000 – £180,000 | 16 – 24 weeks |
Design, engineering and planning fees are on top. Allow a contingency of around 10%, more on an older house. The figures move mostly with what’s underground or behind plaster: foundation depth, underpinning, drain diversions and steel weight. Glazing and finishes move it too, but those are choices.
Before anyone digs, expect roughly four to six months for design, planning and building regulations if a full application is needed. That lead time is the most common reason a project misses the summer it was aimed at.
The brick these jobs are built from has its own London history. After the Great Fire of 1666, the Rebuilding Act of 1667 required new houses in the City to be built of brick or stone and set out four classes of house, with fixed storey heights and wall thicknesses for each. Most of London’s later building control grew from those rules.
Frequently Asked Questions
How much does a double storey extension cost in London?
Typically £90,000 to £180,000 for the build, before kitchens, bathrooms and VAT. Foundations and underpinning are what most often push a job to the top of that range.
Do I need planning permission for a double storey extension?
Often. Permitted development allows it only up to 3 metres deep and at least 7 metres from the rear boundary, with obscure-glazed side windows, and not in a conservation area. Building regulations approval is needed in every case.
What is a wraparound extension?
A side return and a rear extension built as one job, in an L around the back corner of the house. It usually needs full planning permission.
How long does a wraparound extension take?
Usually fourteen to twenty weeks on site, after four to six months of design and approvals. Drain diversions are the most common cause of delay once work starts.
Is it cheaper to build two storeys at once?
Yes, per square metre, by a good margin. Scaffolding, roof and foundations are paid for once, and you go through planning and building control once.
Will my neighbours need to agree?
They can’t veto it, but they’re consulted on a planning application and councils weigh objections about light and overlooking. Party wall notices are separate: two months before work to a shared wall.
Where the new space usually goes
On most of these jobs the ground floor becomes a kitchen-diner. Layout, services and timing for that are covered in kitchen extensions in London.
Planning a project in London?
Talk it through with Force Builders Ltd — straight answers, no obligation. Over 25 years building across London.
Force Builders Ltd is a London building company (Companies House 07049787) delivering house extensions, loft conversions and full refurbishments across Greater London. See our projects or get in touch.