“Trusted builder” is on almost every builder’s van in London. It doesn’t mean anything legally. There’s no licence to be a builder in the UK, and anyone can set up tomorrow and start knocking down walls.

What can be checked is the paperwork around the job, and the law says more about that than most people realise.

A London builder you can rely on

London houses make building work slower than it looks on paper. Most of the stock is Victorian and Edwardian terraces, often with shallow foundations, old lime mortar and decades of alterations nobody recorded. Each borough has its own building control team and its own way of dealing with parking suspensions and skip licences. Access is often through the house.

A builder who knows that prices it in. One who doesn’t finds out on site, and the client pays for it in time or extras.

The law sets a minimum for the work itself. Regulation 7 of the Building Regulations 2010 says building work shall be carried out:

“with adequate and proper materials which— (i) are appropriate for the circumstances in which they are used, (ii) are adequately mixed or prepared, and (iii) are applied, used or fixed so as adequately to perform the functions for which they are designed; and (b) in a workmanlike manner.”

Building Regulations 2010, regulation 7(1)

“In a workmanlike manner” is the actual legal wording. It’s been in building law for a long time, and building control inspectors still use it.

Expert construction solutions for modern homes

Most work on London homes comes down to a few kinds of job. Opening up a dark ground floor into a kitchen and dining area, which nearly always means steel beams and a structural engineer. Converting the loft. A rear or side return extension for more space downstairs.

Each one touches the structure, and each one needs building regulations approval. Before starting, work out where the steel goes, how the new floor or roof is supported, what the neighbours need to be told, and what building control will want to see at each stage. That’s most of what separates a smooth job from one that stops for a week while somebody works out the answer.

Our building services in London

House extensions

A home extension on a London terrace is usually single storey, at the rear or into the side return. Many go up under permitted development, but a lot need full planning, especially in conservation areas.

Building regulations always apply. Foundations are dug and inspected before concrete goes in. The steel beam over the opening into the old house is designed by a structural engineer. On a terrace, the foundations usually come close to the neighbour’s, which means a party wall notice at least a month before digging.

The things that take time are often not the building: party wall agreements, the steel being fabricated, windows and sliding doors on a lead time of six to ten weeks. A typical single storey extension is ten to fourteen weeks on site once it starts.

Loft conversions

A loft conversion needs enough head height first. Measure from the top of the ceiling joists to the underside of the ridge. Under about 2.2 metres, it gets difficult.

A rear dormer often falls under permitted development, within 40 m³ on a terrace and 50 m³ on a semi or detached house. A mansard almost always needs planning. Building regulations apply either way: a new floor, a protected escape route with fire doors and linked smoke alarms, insulation and a proper staircase. There’s more detail on what’s involved in a well-planned loft conversion.

A dormer is usually six to ten weeks on site, with scaffolding up for the whole time. Most families stay in the house.

Home renovations and refurbishments

A full refurbishment of a period house usually means rewiring, new plumbing and heating, new plaster, and often new floors. The structure gets looked at once the old finishes are off, and that’s when the surprises appear: notched joists, a chimney breast removed downstairs with nothing holding up the one above, or lead water pipes still in use.

On houses built before 2000, an asbestos survey should be done before strip-out. It turns up in textured ceilings, floor tiles and old boiler flues.

The order matters, and so does the contingency. Ten per cent is fine on a newer house. On a period property, 15 to 20% is more realistic. There’s a step-by-step version in this guide to a successful home renovation.

General building works

Not every job is a full refurbishment. A lot of work is smaller: structural works, repairs, remodelling, taking out a wall, rebuilding a bay, fixing subsidence damage or a leaking roof.

Small jobs still need the right approvals. Removing a load-bearing wall needs building regulations approval and a structural calculation, even if it’s the only thing being done. Electrical work in a kitchen or bathroom has to be done by a registered electrician or inspected.

Why homeowners choose Force Builders

The honest answer is that most people hire the builder they feel they can talk to, after seeing finished work. Checking the facts behind that feeling takes ten minutes.

Look the company up on Companies House to see how long it’s been trading and whether accounts are filed on time. Check the public liability insurance certificate and its dates. Check the electrician on the NICEIC or NAPIT register and the gas engineer on the Gas Safe Register. Ask for a building control completion certificate from a past job.

A builder that’s honest, organised and consistent won’t mind any of those questions.

Quality workmanship matters

Poor work doesn’t usually show on handover day. It shows a year or two later. Cracks along plasterboard joints where the boards weren’t fixed properly. A shower leaking behind the tiles because only the tray area was tanked. Damp on a solid Victorian wall that was covered in gypsum and vinyl paint.

Building control inspects key stages: foundations, drainage, structure, insulation, and the completion. They don’t check the finish. The quality of plastering, tiling and joinery is down to the builder.

Construction with a practical approach

There’s one law most homeowners have never heard of that applies to every building job: the Construction (Design and Management) Regulations 2015, known as CDM. They cover health and safety on site, and they put duties on the client. For homeowners, those duties pass to the builder:

“Where the client is a domestic client the duties in regulations 4(1) to (7) and 6 must be carried out by— (a) the contractor for a project where there is only one contractor; (b) the principal contractor for a project where there is more than one contractor…”

CDM 2015, regulation 7(1)

In practice that means the builder is responsible for a construction phase plan, for site welfare like a toilet and washing facilities, and for coordinating the trades safely. On bigger jobs, the project has to be notified to the Health and Safety Executive. A builder who’s never heard of CDM is worth asking a few more questions.

Tailored solutions for London properties

Different houses need different solutions. Solid brick walls on a Victorian house need to breathe, so lime plaster and breathable paint often work better than modern gypsum. 1930s semis usually have cavity walls and different problems, like failed wall ties. Flats in mansion blocks need the freeholder’s licence to alter before any work starts, and leases often restrict working hours more strictly than the council does.

A detail that’s right in one house can cause damp or cracking in another.

More than just building work

A lot of a building project isn’t building. Party wall notices to the neighbours. A building control application. A skip licence and a parking suspension from the council. Checking whether the house is in a conservation area or has an Article 4 direction. Getting the completion certificate at the end, which a buyer’s solicitor will ask for when the house is sold.

Some builders handle all of it. Some leave it to the client. Find out which before signing.

Looking for a trusted builder in London, UK?

Get at least three written quotes that price the same scope, and compare what’s included, not just the total. Look at provisional sums for items not chosen yet, like kitchens and tiles, because a low allowance makes a quote look cheaper. There’s more on choosing the right team in our London builders guide, and you can get in touch if you want a quote.

FAQ

How long does a house extension usually take?

A single storey rear extension is usually ten to fourteen weeks on site. Add the time before that for planning, party wall agreements and steel fabrication, which can be another two to four months.

Is a loft conversion worth it in London?

Usually, if there’s enough head height. It adds a bedroom that estate agents count, and stamp duty and moving costs on a London house are often more than the conversion itself.

Do I always need planning permission?

No. Many rear extensions and dormer lofts go under permitted development. Conservation areas, listed buildings, flats and Article 4 areas are the main exceptions. Get a Lawful Development Certificate either way.

What is the difference between renovation and refurbishment?

There’s no legal difference and people use them interchangeably. Builders tend to use refurbishment for updating what’s there, and renovation when layouts or structure change too.

Can you take on smaller jobs as well?

Yes. Removing a wall, rebuilding a bay, repairs after a leak. Smaller jobs still need building regulations approval if they touch the structure.

How do I know if I am choosing the right builder?

Check Companies House, insurance, and the electrician and gas engineer registrations. Visit a finished job and talk to that client.

Will building work turn the whole house upside down?

Yes, for a while. Kitchens and extensions are the worst, because the kitchen is usually out of action for weeks. Lofts are less disruptive until the stairs go in.

Does building work add value to a property?

Extra bedrooms and bigger kitchens usually do. Very personal finishes often don’t. Missing completion certificates can take value off.

What should I sort out before starting a project?

A clear brief, drawings, and a budget with contingency. Check whether the house is in a conservation area and whether party wall notices will be needed.

Why do people choose Force Builders?

That’s for our clients to say, not us. Read the reviews, ask to see finished work and speak to the people we built for.

Looking for a builder you can trust?

Talk it through with Force Builders Ltd — straight answers, no obligation. Over 25 years building across London.

Force Builders Ltd